Question: Question Workspace Hint ( s ) Check My Work Spreadsheet Suppose a manufacturer of copiers has concluded that a 7 0 percent learning curve applies

Question Workspace
Hint(s) Check My Work
Spreadsheet
Suppose a manufacturer of copiers has concluded that a 70 percent learning curve applies to the time a beginning service technician takes to install copy machines. Use the Learning Curve Excel template to answer the following questions:
If the time required to install the first copy machine is estimated to be six hours, what is an estimate of the time required by a new technician to install the second and third copiers? Round your answers to one decimal place.
For x =2 it takes
4.2
hours
For x =3 it takes
3.4
hours
If the learning rate changes to 65 or 95 percent, what is an estimate of the time required by a new technician to install the second and third copiers? Round your answers to one decimal place.
For x =2 and a 65% LC, it takes
4.6
hours
For x =3 and a 65% LC, it takes
3.8
hours
For x =2 and a 95% LC, it takes
5.7
hours
For x =3 and a 95% LC, it takes
5.5
hours

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!