Question: QUESTIONS: Assume a project is defined by the data provided in the attached table. Use the information to answer the following questions: A) How many

QUESTIONS:
Assume a project is defined by the data provided in the attached table. Use the information to answer the following questions:
A) How many paths are there?
B) What is the critical path?
C) What is the minimum completion time for this project?
D) If the only indirect project costs are $750, but you are fined $2200 per day past 15 days of project duration, estimate the total project costs (round to whole number) under the current duration.
E) Your manager doesnt want to pay any fines. Crash the project and determine the cost savings (round to 2 decimal places).
E4 x fx Cost/day TAB C EF 1 Assume a project is defined by the data given in the table: G H 2 Crashing (Max) Normal Time Crashing Activity Predecessor Time 1 (days) | (days) A - 15 2 6 B 1 - 7 1 7 CA 10 1 8 DA 92 GE DB 6 1 F C 7 2 GB 41 E, D, G 6 1 Cost/day $750 $1,100 $700 $1,500 $800 $850 $900 $1,100 13 14 15 16 18 19 22 24 26 27 28 29 30 31Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
