Question: QUESTIONS FROM HIZE CHAPTER 1 0 1 . The following bar chart shows the activities to complete a project in 6 months ( each cell

QUESTIONS FROM HIZE CHAPTER 10
1. The following bar chart shows the activities to complete a project in 6 months (each cell represents
1 month). The total project cost is $700.
ACTIVITY COST MONTH
1
MONTH
2
MONTH
3
MONTH
4
MONTH
5
MONTH
6
A $100
B $30
C $40
D $80
E $20
F $50
G $70
H $30
J $200
K $60
L $20
After 2 months, activities A, B, half of C, and half of D are completed for a cost of $200. For this point
in time (2 months since the start date), what are the values of budgeted cost of work performed,
budgeted cost of work scheduled and the actual cost of work performed.
Option 1:
ACWP = $200
BCWP = $190
BCWS = $170

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!