Question: ACWP = $500 EARNED VALUE 41. The following bar chart shows the activities to complete a project in six months (each cell represents 1 month).

 ACWP = $500 EARNED VALUE 41. The following bar chart shows

ACWP = $500

EARNED VALUE 41. The following bar chart shows the activities to complete a project in six months (each cell represents 1 month). After 3 months on the job (the data date), activities A, B, and D are completed; 30% of Activity F; 60% of Activity C; and 50% of Activity E was completed. Activities G, H, J, and K have not been started. Using the earned value concepts, determine the cost and schedule variance. Also report whether the project is over or under budget, and behind or ahead of schedule. SHOW ALL YOUR WORK INCLUDING FORMULAE USING MS WORD Activity Month 1 Month 2 Month 3 Month 4 Month 5 Month 6 LIOTMOOO Cost $50 $120 $80 $200 $120 $300 $60 $70 $50 $60 Data Date BCWS = (4 points) BCWP=_ (4 points) ACWP= (4 points) The project is: (underline the correct answer - (4 points each) a) Over budget b) Under budget The project is: (underline the correct answer - (4 points each) a) Behind schedule b) Ahead of schedule EARNED VALUE 41. The following bar chart shows the activities to complete a project in six months (each cell represents 1 month). After 3 months on the job (the data date), activities A, B, and D are completed; 30% of Activity F; 60% of Activity C; and 50% of Activity E was completed. Activities G, H, J, and K have not been started. Using the earned value concepts, determine the cost and schedule variance. Also report whether the project is over or under budget, and behind or ahead of schedule. SHOW ALL YOUR WORK INCLUDING FORMULAE USING MS WORD Activity Month 1 Month 2 Month 3 Month 4 Month 5 Month 6 LIOTMOOO Cost $50 $120 $80 $200 $120 $300 $60 $70 $50 $60 Data Date BCWS = (4 points) BCWP=_ (4 points) ACWP= (4 points) The project is: (underline the correct answer - (4 points each) a) Over budget b) Under budget The project is: (underline the correct answer - (4 points each) a) Behind schedule b) Ahead of schedule

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!