Question: QUESTIONS FROM HIZE CHAPTER 1 0 1 . The following bar chart shows the activities to complete a project in 6 months ( each cell
QUESTIONS FROM HIZE CHAPTER The following bar chart shows the activities to complete a project in months each cell represents month The total project cost is $ ACTIVITY COST MONTH MONTH MONTH MONTH MONTH MONTH A $ B $ C $ D $ E $ F $ G $ H $ J $ K $ L $ After months, activities A B half of C and half of D are completed for a cost of $ For this point in time months since the start date what are the values of budgeted cost of work performed, budgeted cost of work scheduled and the actual cost of work performed. Option : ACWP $ BCWP $ BCWS $