Question: quickly please!!! courses / PRODUCTION MANAGEMENT 1-Lecture-1201 - 3 / General / MTR An activity on a PERT network has these time estimates: optimistic -

quickly please!!!
quickly please!!! courses / PRODUCTION MANAGEMENT
courses / PRODUCTION MANAGEMENT 1-Lecture-1201 - 3 / General / MTR An activity on a PERT network has these time estimates: optimistic - 2. most likely = 5, and pessimistic - 10. What is its expected activity time? Select one: o a. 5.33 b. 32.00 c. 10.67 d. 5.67 e. 5.00 Next pas Jump to