Question: An activity on a PERT network has these time estimates: optimistic = 3, most likely = 4, and pessimistic = 5. Its expected time is
An activity on a PERT network has these time estimates: optimistic = 3, most likely = 4, and pessimistic = 5. Its expected time is
a. 5
b. 4
c. 3.5
d. 4.5
e. 12
The Dulac Box plant produces 500 cypress packing boxes in two 10-hour shifts. Due to higher demand, they have decided to operate three 8-hour shifts instead. They are now able to produce 600 boxes per day. What has happened to production?
a. It has increased by 8.1%.
b. It has increased by 9.1%.
c. It has increased by 50 sets/shift.
d. It has increased by 37.5 sets/hr.
e. no change