Question: Rachel is working on a project that technically allows three activities to be done at the same time. If they were to be implemented at

Rachel is working on a project that technically allows three activities to be done at the same time. If they were to be implemented at the same time, she would need 5 contractors in order for the activities to be completed on time. There are only 3 contractors available for her to use. This is an example of what type of resource constraint?
Select one:
A.
People
B.
Equipment
C.
Information
D.
Materials