Question: Radiant Systems allocates manufacturing overhead based on machine hours. Each connector should require 10 machine hours. According to the static budget, Radiant expected to incur

Radiant Systems allocates manufacturing overhead based on machine hours. Each connector should require 10 machine hours. According to the static budget, Radiant expected to incur the following: (Click the icon to view the static budget information.) During August, Radiant actually used 750 machine hours to make 86 connectors and spent $5,100 in variable manufacturing costs and $7,800 in fixed manufacturing overhead costs. Calculate the variable overhead efficiency variance for Radiant. More Info OA. $413 U OB. $1,101 F OC. $688 F 800 machine hours per month (80 connectors x 10 machine hours per connector) $5,000 in variable manufacturing overhead costs $7,250 in fixed manufacturing overhead costs OD. $275 F Click to select your answer. Print Done