Question: Rafner Manufacturing has the following budgeted data for its two production departments. Budgeted Data Assembly Finishing Overhead cost $ 1 , 5 3 5 ,

Rafner Manufacturing has the following budgeted data for its two production departments.
Budgeted Data Assembly Finishing
Overhead cost $ 1,535,100 $ 1,011,700
Direct labor hours 12,900 direct labor hours 19,100 direct labor hours
Machine hours 5,100 machine hours 15,100 machine hours . What is the Assembly department overhead rate using direct labor hours?
What is the Finishing department overhead rate using machine hours?