Rammazzotti, Inc., is looking for feedback on company performance. The company compares the budget for the year
Question:
Rammazzotti, Inc., is looking for feedback on company performance. The company compares the budget for the year with the actual costs. Data have been collected below:
Rammazzotti Inc., had the following budgeted data:
Unit sales for 2014 28,000
Unit production for 2014 28,000
Budgeted fixed overhead for 2014:
Supervision $ 800
Depreciation 2,000
Rent 100
Budgeted variable costs per unit:
Direct materials $0.15
Direct labor 0.20
Supplies 0.02
Indirect labor 0.05
Power 0.02
The following actually occurred:
Actual unit sales for 2014 27,000
Actual unit production for 2014 29,000
Actual fixed overhead for 2014:
Supervision $ 850
Depreciation 2,000
Rent 150
Actual variable costs:
Direct materials $3,500
Direct labor 4,900
Supplies 530
Indirect labor 1,250
Power 470
The flexible budget variance for indirect labor for 2014 is
a. $200 F.
b. $150 F.
c. $150 U.
d. $200 U.
The flexible budget variance for total cost for 2014 is
a. $2,010 F.
b. $240 F.
c. $1,620 F.
d. $850 F.