Question: The following labor hours data have been collected for a nanotechnology project for periods 1 through 6. Compute the SV, CV, SPI, and CPI for

The following labor hours data have been collected for a nanotechnology project for periods 1 through 6. Compute the SV, CV, SPI, and CPI for each period. Plot the EV and the AC on the summary graph provided (or a similar one). Plot the SPI, CPI, and PCIB on the index graph provided (or a similar one). What is your assessment of the project at the end of period6?
The following labor hours data have been collected for a

Period SPI CPI PCIB SPI= EV/PV CPI EV/AC PCIB EV/BAC Summary Graph 6000 14000 12000 10000 8000 6000 2.20 2.00 1.80 1.60 1.40 1.20 1.00 .80 ly 0 1 2 34 5 6 7 8 9 10 11 12 13 14 15 Time periods .20 Time periods

Step by Step Solution

3.40 Rating (166 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

After 6 time periods the project is roughly 66 complete and so far work on the project has taken 160... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

177-B-M-L-P-M (1468).docx

120 KBs Word File

Students Have Also Explored These Related Management Leadership Questions!