Question: Raw Material Finished Units Cut Sew Press p = 10 min/unit p = 12 min/unit p = 4 min/unit In a textile factory there are

Raw Material Finished Units Cut Sew Press p = 10

Raw Material Finished Units Cut Sew Press p = 10 min/unit p = 12 min/unit p = 4 min/unit In a textile factory there are three steps on a worker-paced line producing T-shirts. There is one worker per station and no inventory is stored between the steps. The processing times are Cut: 10 minutes/shirt Sew: 12 minutes/shirt Press: 4 minutes/shirt Where is the bottleneck? Select one: O a. Cut O b. Sew O c. Press O d. Cannot be determined from the information given