Question: Ray: I will use a CPM technique to develop the plan. Patricia: That sounds great. We will be using the new gates starting from 6
Ray: I will use a CPM technique to develop the plan.
Patricia: That sounds great. We will be using the new gates starting from 6 AM to 10 PM every day of the week. As you know, all our employees work two shifts, morning shift from 6 AM to 2 PM and the afternoon shift from 2 PM to 10 PM. I need to tell David about the number of new customer service people we need to hire for the additional gates. I promised to get back to him in a week.
Ray: From the passenger forecast, I can use our regular rule of one agent for every hundred passengers. I will also make sure that every employee gets two consecutive days off. I will also add the usual 10% additional staff to cover vacations, sick-days, and absenteeism.
Patricia: You seem to be a quick learner and your knowledge of our operations is a definite plus. One last thing which you may be able to help me with this week is responding to Paul, our V.P. of communications, about delays in our flights. Typically, in our industry, three to fifteen percent of the flights are late. Paul wanted to know how we are doing compared to the industry. I had asked flight operations to send the sample data about flight delays.
Major Tasks and Completion Time
(Prepared in Conjunction with Vendors)
The major tasks required to be completed for finishing the gate area at Newark Airport has been determined with the help of vendors and Eco-Jet operations personnel.
| Task ID | Description of Tasks | Immediate Predecessors | a | m | b | Responsible Party |
| A | Award Contract to Vendor |
| 2 | 2 | 4 | Eco-Jet |
| B | Finalize Telecom Wiring Plan |
| 2 | 3 | 5 | Eco-Jet |
| C | Finalize Electrical & Plumbing Plan |
| 1 | 2 | 3 | Eco-Jet |
| D | Prepare (Rough) floors and walls | A | 12 | 16 | 20 | Vendor |
| E | Acquire all furniture and fixtures | A, B, C | 2 | 2 | 2 | Eco-Jet |
| F | Install telecom wiring as planned | B, D | 11 | 14 | 19 | Vendor |
| G | Install electrical wiring as planned | C, D | 8 | 10 | 12 | Vendor |
| H | Install rough plumbing as planned | C, D | 3 | 4 | 6 | Vendor |
| I | Finish walls | E, F, G, H | 7 | 7 | 7 | Vendor |
| J | Finish Floors | D | 3 | 3 | 3 | Vendor |
| K | Install furniture and counters | F, G, J | 12 | 14 | 18 | Vendor |
| L | Install telecom and network jacks | K | 3 | 4 | 5 | Vendor |
| M | Finish plumbing work | I | 2 | 2 | 2 | Vendor |
| N | Finish Electrical work | I, K | 3 | 3 | 3 | Vendor |
| O | Test all computers | L, N | 1 | 2 | 5 | Eco-Jet |
| P | Test phones, announcements etc. | L, N | 2 | 3 | 4 | Eco-Jet |
| Q | Inspect entire premises | M, O, P | 1 | 1 | 1 | Eco-Jet |
| R | Project Completion & Sign-off | Q | 1 | 1 | 1 | Eco-Jet |
Notes:
- a represents the optimistic time in days to perform a task.
- m represents the most likely time in days to perform a task.
- b represents the pessimistic time in days to perform a task.
- The time estimates remain the same for all three vendor
Step by Step Solution
There are 3 Steps involved in it