Question: re the project lead of a large application development project to implement an e - commerce portal for you re now at the end of
re the project lead of a large application development project to implement an ecommerce portal for you re now at the end of system testing and would like to understand how robust the initial requirements pha was. Which of the following would be the best metric for this?
one:
Number of initial requirements end of requirements phasetotal number of requirements currently
None of the other answers is correct
Number of defects by origin phase
Number of change requests post requirements phase