Question: Read the case study below and answer ALL of the questions that follow SOUTH AFRICA R 2 2 million paid for no work 3 0

Read the case study below and answer ALL of the questions that follow
SOUTH AFRICA
R22 million paid for no work
30 September 2010-11:30BY SOWETAN
TimesLIVE
The departments of public works, roads, and transport, along with the provincial health department and treasury, announced yesterday that it was willing to pay Tsogo Developers R22 million despite the
company's failure to complete construction on the R456,5m Brits Hospital. Tsogo and llima Projects were awarded the R456,5 million contract in 2005 and construction began on November 25,2008.
But work stopped in May this year after llima was liquidated. At the time llima had a portfolio of construction projects worth more than R1-billion and employed about 700 people. Public works spokesperson Roberta Makhambeni told Sowetan yesterday that the department had good reason to pay. "In order to fast-track the re-appointment of the new contractor, the department opted for a settlement
instead of the final account, which would have delayed the process," Makhambeni said.
Now a new contractor - JR Stock and Stocks, who lost out in the initial bidding for the contract - has been hired to complete the project. The hospital is scheduled to open in July 2012. Makhambeni said
"they were second-best (in the initial bidding process) and had the right grading". Tsogo and llima were paid R57 million before construction was stopped in May. Ilima's financial problems affected other projects, among them:
-the R137 million for a government office complex in Vryburg, Northwest.
-About R35 million for the construction of a psychiatric hospital in Sterkfontein, Krugersdorp, Gauteng.
-R16 million for the construction of a taxi rank in Mabopane, north of Pretoria.
-More than R60 million for the construction of 1500 houses for Mogale City municipality; and
-R450 million worth of construction work in Eastern Cape.
Source:
https://www.timeslive.co.za/news/south-africa/2010-09-30-r22-million-paid-for-no-work/
Question 2: Evaluation of Schedule Management Techniques(25 Marks)
Considering the timeline from the awarding of the contract to the cessation of work and subsequent re-appointment of a new contractor:
a. Evaluate the effectiveness of the schedule management techniques initially employed. Utilise concepts from GanttCharts, Project Network Diagrams, and Schedule Compression to critically analyse the scheduling decisions made.
b. Propose a comprehensive schedule management plan, including how critical path analysis could have been used to predict and possibly mitigate the delay in project completion.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!