Question: reate a Network Diagram ( Activity on Node ) schedule using the following Activity Duration ( Days ) Predecessor A 4 - B 3 A

reate a Network Diagram (Activity on Node) schedule using the following
Activity Duration (Days) Predecessor
A 4-
B 3 A
C 4 A
D 2 B, C
E 4 C
F 2 D
G 4 D, E
H 1 E
I 6 F, G, H
5)(5 Points) Determine the total and free float of all activities in problem #4 above