Question: reate a Network Diagram ( Activity on Node ) schedule using the following Activity Duration ( Days ) Predecessor A 4 - B 3 A
reate a Network Diagram Activity on Node schedule using the following
Activity Duration Days Predecessor
A
B A
C A
D B C
E C
F D
G D E
H E
I F G H
Points Determine the total and free float of all activities in problem # above