Question: Question 6 (Principles of project management) Given the table below: Activity Predecessor Duration (Days) A - 5 B A 4 C A 5 D B
Question 6 (Principles of project management)
Given the table below: Activity Predecessor Duration (Days) A - 5 B A 4 C A 5 D B 6 E C 3 F D, E 4
6.1 Construct a project network diagram (activity on node diagram). (2)
6.2 Determine the following on every node: Early start, Early finish, Late start, Late finish by copying and filling in the following table: Activity Duration Early Start Early Finish Late Start Late Finish Slack A 5 B 4 C 5 D 6 E 3 F 4 . (4)
6.3 Determine the critical path and its duration. (2)
6.4 Identify activity (ies) with a slack on the project. (2) [10]