Question: Reedy Builders, Inc. is using the completed-contract method for a $12,500,000 contract that will take three years to complete. Data at December 31, 2015, the

Reedy Builders, Inc. is using the completed-contract method for a $12,500,000 contract that will take three years to complete. Data at December 31, 2015, the end of the first year, are as follows: Costs incurred to date $6,240,000 Estimated costs to complete 6,660,000 Billings to date 5,920,000 Collections to date 5,540,000 The gross profit or loss that should be recognized for 2015 is