Question: . Refer to Figure 3 . Which is not true about the PDM for the project? Select the most appropriate one. a . The project

. Refer to Figure 3. Which is not true about the PDM for the project? Select the most appropriate one.
a. The project duration is 9.
b. The total float of C is 0.
c. The free float of B is 0.
d. None of the above is true.Figure 3(Problem 3 & 4)