Question: Refer to Table 1 below. This table shows your estimates of optimistic, likely and pessimistic durations for activities contained within one of the works' packages.
Refer to Table below. This table shows your estimates of optimistic, likely and pessimistic durations for activities contained within one of the works' packages.
Table Estimated activity times for activities included within a work package
Activity
Optimistic duration weeks
Likely duration weeks
AB
Pessimistic duration weeks
BC
BD
CB
CF
CG
DE
EH
PH
GH
G
HI
Time left
a Using a programme evaluation and review technique PERT approach, draw a project schedule showing all activities, the critical path and project mean duration. marks
marks b Calculate the probability of the work package being completed by week
Discuss the main applications and limitations of PERT based project planning and examine the likely suitability of a PERT based approach in the case study. marks
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock