Question: Refer to the activity network table below. Enter this information using MS Project to produce a Gantt chart. Assume that each resource has been assigned

Refer to the activity network table below. Enter this information using MS Project to produce a Gantt chart. Assume that each resource has been assigned to the project activity on a full-time (8 hours/day or 40 hours/week) basis.

ActivityDurationPredecessorsResource Assigned

A. User survey4NoneGail Wilkins

B. Coding12ATom Hodges

C. Debug5BWilson Pitts

D. Design interface6A, CSue Ryan

E. Develop training5DReed Taylor

a. What is the projects Duration?

b. Select the Resource Usage view that identifies the total number of hours and daily commitments of each project team member. What member(s) of the project team is/are overloaded?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!