Question: Refer to the activity network table below. Enter this information using MS Project to produce a Gantt chart. Assume that each resource has been assigned
Refer to the activity network table below. Enter this information using MS Project to produce a Gantt chart. Assume that each resource has been assigned to the project activity on a full-time (8 hours/day or 40 hours/week) basis.
ActivityDurationPredecessorsResource Assigned
A. User survey4NoneGail Wilkins
B. Coding12ATom Hodges
C. Debug5BWilson Pitts
D. Design interface6A, CSue Ryan
E. Develop training5DReed Taylor
a. What is the projects Duration?
b. Select the Resource Usage view that identifies the total number of hours and daily commitments of each project team member. What member(s) of the project team is/are overloaded?
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
