Question: Refer to the activity network table below. Enter this information using MS Project to produce a Gantt chart. Assume that each resource has been assigned

Refer to the activity network table below. Enter this information using MS Project to produce a Gantt chart. Assume that each resource has been assigned to the project activity on a full-time (8 hours/day or 40 hours/week) basis.
Refer to the activity network table below. Enter this information

Activity A. User survey B. Coding C. Debug D. Design interface 6 E. Develop training 5 Duration Predecessors Resource Assigned Gail Wilkins Tom Hodges Wilson Pitts Sue Ryan Reed Taylor None 12 A, C

Step by Step Solution

3.41 Rating (176 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Microsoft product screen shots reprinted with permission from ... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

663-B-M-L-P-M (2184).docx

120 KBs Word File

Students Have Also Explored These Related Management Leadership Questions!