Question: Refer to the earned value table for Project Terrace, for the end of day 6, and answer question 3-8. All dollar amounts are in hundreds.
Refer to the earned value table for Project Terrace, for the end of day 6, and answer question 3-8. All dollar amounts are in hundreds.
The planned value is:
The earned value is:
The actual cost so far is:
The SPI is:
The estimated time to completion is:
Duration in days 6 9 12 3 15 Planned Value % Comp Earned Value 2 3 1 100 5 3 4 6 Activity Landscape Design Retaining wall Dirt work Move utilities Sprinkler system Planting Planned Cost Cumulative Planned Cost Actual Cost Cumulative Actual Cost 2 3 4 50 5 10 0 3 12 15 0 2 8 14 9 24 33 48 2 2 10 9 Duration in days 6 9 12 3 15 Planned Value % Comp Earned Value 2 3 1 100 5 3 4 6 Activity Landscape Design Retaining wall Dirt work Move utilities Sprinkler system Planting Planned Cost Cumulative Planned Cost Actual Cost Cumulative Actual Cost 2 3 4 50 5 10 0 3 12 15 0 2 8 14 9 24 33 48 2 2 10 9
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
