Question: Refer to the earned value table for Project Terrace, for the end of day 6, and answer question 3-8. All dollar amounts are in hundreds.

Refer to the earned value table for Project Terrace, for the end of day 6, and answer question 3-8. All dollar amounts are in hundreds.

The planned value is:

The earned value is:

The actual cost so far is:

The SPI is:

The estimated time to completion is:Refer to the earned value table for Project Terrace, for the end

Duration in days 6 9 12 3 15 Planned Value % Comp Earned Value 2 3 1 100 5 3 4 6 Activity Landscape Design Retaining wall Dirt work Move utilities Sprinkler system Planting Planned Cost Cumulative Planned Cost Actual Cost Cumulative Actual Cost 2 3 4 50 5 10 0 3 12 15 0 2 8 14 9 24 33 48 2 2 10 9 Duration in days 6 9 12 3 15 Planned Value % Comp Earned Value 2 3 1 100 5 3 4 6 Activity Landscape Design Retaining wall Dirt work Move utilities Sprinkler system Planting Planned Cost Cumulative Planned Cost Actual Cost Cumulative Actual Cost 2 3 4 50 5 10 0 3 12 15 0 2 8 14 9 24 33 48 2 2 10 9

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Finance Questions!