Question: Could someone show the steps for the answer. its urgent please 1. Use the earned value table for Project Terrace to calculate their estimated cost

Could someone show the steps for the answer. its urgent please
1. Use the earned value table for Project Terrace to calculate their estimated cost to completion (all dollar amounts are in hundreds) Duration in days B 6 10 12 15 | Comp 2 3 1 3 100 50 5 4 2 Activity Landscape design Retaining wall Dirt work Move utilities Sprinkler system Planting Plan Cumulative Actual 16 3 10 4 3 10 0 8 10 14 24 9 33 12 15 148 12 12. 18 A) $4,285 B) $4,800 C) $4,532 D) $3,604 Answer: AStep by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock