Question: Refer to the predecessor table and the duration table for the following project; Activity Immediate Predecessors A - B A C B D A E
Refer to the predecessor table and the duration table for the following project;
| Activity | Immediate Predecessors |
| A | - |
| B | A |
| C | B |
| D | A |
| E | C, D |
| Activity | Duration |
| A | 12 |
| B | 4 |
| C | 1 |
| D | 7 |
| E | 3 |
(b) Use the two-pass method to determine the ES, EF, LS and LF for all activities. Each answer should be entered only as a number.