Question: Refer to the predecessor table and the duration table for the following project; Activity Immediate Predecessors A - B A C B D A E

Refer to the predecessor table and the duration table for the following project;

Activity

Immediate Predecessors

A

-

B

A

C

B

D

A

E

C, D

Activity

Duration

A

12

B

4

C

1

D

7

E

3

(b) Use the two-pass method to determine the ES, EF, LS and LF for all activities. Each answer should be entered only as a number.