Question: Refer to the predecessor table and the duration table for the following project; Activity Immediate Predecessors A - B A C B D A E

Refer to the predecessor table and the duration table for the following project;

Activity

Immediate Predecessors

A

-

B

A

C

B

D

A

E

C, D

Activity

Duration

A

12

B

4

C

1

D

7

E

3

(c) Use the enumeration method to identify all paths, and path lengths. Enter your answers in the blank space below. (Remember to provide each path, as well as the lengths of each path).