Question: Refereeing the table below what is the total duration for the summary activity, Business Requirements Definition? WBS Activity Predecessors Resource Name Duration TRN 0 0
Refereeing the table below what is the total duration for the summary activity, Business Requirements Definition?
WBS
Activity
Predecessors
Resource Name
Duration
TRN
Business Requirements Definition
TRN
Gather requirements
TRN FS
Technical Experts, Software
Architects, Project Manager, PMO
Days
TRN
Document business requirements
TRN FS
Technical Experts, Software Architects, Project Manager
Days
TRN
Review requirements
TRN FS
Technical Experts, Software Architects, Project Manager
Day
TRN
Obtain authorization
TRN FS
Project Manager, PMO
Day
a
days
b
days
c
days
d
day
Jump to
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock