Question: Refereeing the table below what is the total duration for the summary activity, Business Requirements Definition? WBS Activity Predecessors Resource Name Duration TRN 0 0

Refereeing the table below what is the total duration for the summary activity, Business Requirements Definition?
WBS
Activity
Predecessors
Resource Name
Duration
TRN001.3
Business Requirements Definition
TRN001.3.1
Gather requirements
TRN001.2 FS
Technical Experts, Software
Architects, Project Manager, PMO
4 Days
TRN001.3.2
Document business requirements
TRN001.3.1 FS
Technical Experts, Software Architects, Project Manager
2 Days
TRN001.3.3
Review requirements
TRN001.3.2 FS
Technical Experts, Software Architects, Project Manager
1 Day
TRN001.3.4
Obtain authorization
TRN001.3.3 FS
Project Manager, PMO
1 Day
a.
6 days
b.
2 days
c.
8 days
d.
1 day
Jump to...

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!