Question: Reference: IBM: The Iterative Software Development Method What are the two choices Lalonde has? If you think he has more than 2 choices, please list
Reference: IBM: The Iterative Software Development Method

What are the two choices Lalonde has? If you think he has more than 2 choices, please list all the choices he has Who should Lalonde and Mayor involve in the decision ?regarding the change request The Rational team is at their last 5 weeks of the entire development period of 18 months i.e. 72 weeks. The RAD team would need 6 weeks of time to go thru the iterative software development cycle where 4 weeks are allotted to planning, design, and implementation and the nal 2 weeks are for the testing phase. How would you determine where to cut a week '?off the schedule to get it down to 5 weeks