Question: THE iterative software development method. Just read the case thoroughly and answer the below-mentioned 3 questions. Here are the three questions to be answered: 1.

THE iterative software development method. Just read the case thoroughly and answer the below-mentioned 3 questions. Here are the three questions to be answered:

1. What are the two choices Lalonde has? If you think he has more than 2 choices, please list all the choices he has

2. Who should Lalonde and Mayor involve in the decision regarding the change request?

3. The Rational team is at their last 5 weeks of the entire development period of 18 months i.e. 72 weeks. The RAD team would need 6 weeks of time to go thru the iterative software development cycle where 4 weeks are allotted to planning, design, and implementation and the final 2 weeks are for the testing phase. How would you determine where to cut a week off the schedule to get it down to 5 weeks?

Step by Step Solution

3.51 Rating (154 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

What are the two choices Lalonde has The two choices Lalonde has is Choosing not to add additional features during the final phases and instead go directly to code freeze after the testing phase and D... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

625e8ea42392b_99732.docx

120 KBs Word File

Students Have Also Explored These Related Finance Questions!