Question: Referring to the table, if you are using the earliest due date , what will be the best sequence? Jobs Machine 1 ( in Days

Referring to the table, if you are using the earliest due date , what will be the best sequence?

Jobs

Machine 1

( in Days )

Machine 2

( in Days )

Due Dates

A

8

3

12

B

1

2

6

C

6

5

13

D

3

2

5

E

4

6

10

a.

DBEAC

b.

DEACB

c.

DBCAE

d.

DEBCA

e.

DACEB