Question: Regarding the project stakeholders and roles, which does not correctly describe them? Select the most appropriate one. Project management staff Perform project management activities such
Regarding the project stakeholders and roles, which does not correctly describe them? Select the most appropriate one.
Project management staff Perform project management activities such as scheduling and budgeting
Project staff Carry out the work of creating the project deliverables
Sellers Include vendors, suppliers, or contractors
Business partners Internal or external stakeholders who approve the project deliverables