Question: Relevant information for a project consisting of activities A , B , dots, H is provided in the table below and the project network is

Relevant information for a project consisting of activities A,B,dots,H is provided in the table below and the project network is provided.
\table[[Activity,Time (in Weeks),Cost,\table[[Immediate],[Predessors]]],[Normal,Crash,Normal,Crash,],[A,5,5,$1450,$1450,NA],[B,2,1,$550,$750,A],[C,5,3,$1850,$2030,A],[D,6,5,$800,$840,B, C],[E,5,4,$650,$690,B, C],[F,3,2,$900,$915,D],[G,4,2,$1550,$1584,E],[H,3,1,$1900,$2260,F, G]]
When all activities are completed in normal time, what is the project completion time?
To reduce project completion time by 1 week at minimum cost, which activity, or activities should be crashed? Enter the letter for the activity (one character in capital), or letters for the activities in capitals (two characters in capitals)(e.g.'B','AH').
What is the incremental cost to reduce project completion time by 1 week at minimum cost?
Please help ASAP?
 Relevant information for a project consisting of activities A,B,dots,H is provided

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!