Question: Remaining Time: 1 hour, 12 minutes, 53 seconds. Question Completion Status: Consider the following MPS schedule: Week Forecast 50 75 80 Orders 100 22 |
Remaining Time: 1 hour, 12 minutes, 53 seconds. Question Completion Status: Consider the following MPS schedule: Week Forecast 50 75 80 Orders 100 22 | 67 10 Projected Available Balance Available to Promise MPS 150 200 150 Using the discrete available-to-promise (ATP) logic to the complete the schedule, what is earliest time that an order of 75 units can be promised? Week 4 Week 2 Week 6 Week 8 tosalonmurs Save As Answers Click Save and submit to see and submit. Click Save All Au Search o at 9