Question: Repeat the comparison of processes A and B using Equivalent Uniform Annual Cost (EUAC), assuming an interest rate of 3%. In the space below, show

Repeat the comparison of processes A and B using Equivalent Uniform Annual Cost (EUAC), assuming an interest rate of 3%. In the space below, show your calculations using factor notation, e.g. (P/F,i,n).

Process A Process B First Cost $550,000 $650,000 Salvage $70,000 $80,000 Annual Savings $50,000 $60,000 Maintenance $2000 every 2 years $1000 occurs every other year, starting the first year and increases by $600 each time Service Life 18 15 Repeat the comparison of processes A and B using Equivalent Uniform Annual Cost (EUAC), assuming an interest rate of 3%. In the space below, show your calculations using factor notation, e.g. (P/F,i,n). According to the EUAC, which process should they choose? a. None b. Process A O c. Process B O d. They are equivalent