Question: Replace X with 32 and please show excel formulas!! 4. a. Complete the following MPS time-phased record: (25 points) Toaster Week 1 2 3 4

Replace X with 32 and please show excel formulas!!

4.

a. Complete the following MPS time-phased record: (25 points)

Toaster

Week

1

2

3

4

5

6

7

8

Gross Requirements

35

20

2+X

25

3+X

25

4+X

25

Orders

8

9

6

4

2

1

Projected Available Balance

X

Available-to-promise

MPS

MPS Lot Size = X

The following events occurred during week 1:

- Actual demand during week 1 was only 28 units

- The forecast for week 9 is 6 + X

- An order for 4 in week 2 was accepted.

- An order for 3 in week 4 was accepted.

- An order for 2 in week 3 was accepted.

- The MPS in week 1 (if any) was produced at the 85% (round up to the nearest integer)

b. Update the record below after rolling through time.

Toaster

Week

2

3

4

5

6

7

8

9

Gross Requirements

20

5+X

25

5+X

25

5+X

25

6+X

Orders

Projected Available Balance

Available-to-promise

MPS

MPS Lot Size = X

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!