Question: Replace X with 32 and please show excel formulas!! 4. a. Complete the following MPS time-phased record: (25 points) Toaster Week 1 2 3 4
Replace X with 32 and please show excel formulas!!
4.
a. Complete the following MPS time-phased record: (25 points)
Toaster
| Week |
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
| Gross Requirements |
| 35 | 20 | 2+X | 25 | 3+X | 25 | 4+X | 25 |
| Orders |
| 8 | 9 | 6 | 4 | 2 | 1 |
|
|
| Projected Available Balance | X |
|
|
|
|
|
|
|
|
| Available-to-promise |
|
|
|
|
|
|
|
|
|
| MPS |
|
|
|
|
|
|
|
|
|
MPS Lot Size = X
The following events occurred during week 1:
- Actual demand during week 1 was only 28 units
- The forecast for week 9 is 6 + X
- An order for 4 in week 2 was accepted.
- An order for 3 in week 4 was accepted.
- An order for 2 in week 3 was accepted.
- The MPS in week 1 (if any) was produced at the 85% (round up to the nearest integer)
b. Update the record below after rolling through time.
Toaster
| Week |
| 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 |
| Gross Requirements |
| 20 | 5+X | 25 | 5+X | 25 | 5+X | 25 | 6+X |
| Orders |
|
|
|
|
|
|
|
|
|
| Projected Available Balance |
|
|
|
|
|
|
|
| |
| Available-to-promise |
|
|
|
|
|
|
|
|
|
| MPS |
|
|
|
|
|
|
|
|
|
MPS Lot Size = X