Question: Resource - limited scheduling attempts a schedule in which the number of resources is limited and Question 3 3 options: the schedule may be extended
Resourcelimited scheduling attempts a schedule in which the number of resources is limited and
Question options:
the schedule may be extended to keep the resource limits
the schedule is shortened because the limit for resources is raised.
the shortest schedule is developed by reducing the project scope.
priorities are given to the activities to limit the time for each activity.