Question: Resource Planning Complete the Projected on Hand Inventory and Planned Order Release rows. Item A 2 40 3 35 | 4 | 5 55 30

Resource Planning Complete the Projected on Hand

Resource Planning Complete the Projected on Hand Inventory and Planned Order Release rows. Item A 2 40 3 35 | 4 | 5 55 30 20 15 Gross Requirements Scheduled Receipts Projected on Hand Inventory | 35 Planned Order Releases Q = 25, LT = 2; SS = 10 Upload the question with your answer in a file, acceptable file formats are: Excel and Word