Question: Resource smoothing revises the schedule to use better use resources. Which of the following is true: Question 14 options: Can be applied to activities on
Resource smoothing revises the schedule to use better use resources. Which of the following is true: Question 14 options: Can be applied to activities on the critical path Resource leveling and resource smoothing are the same. Only applies to activities with slack. The duration of the project is not changed