Question: Resources should be estimated against which entity: Question 4 options: The Risk Breakdown Structure The schedule activities The deliverables level of the WBS Critical project

Resources should be estimated against which entity: Question 4 options: The Risk Breakdown Structure The schedule activities The deliverables level of the WBS Critical project constraints