Question: REVIEW THE INTEGRATED PROGRAM MANAGEMENT REPORT (ipmr) EXCERPT FOR THE prime VEHICLE. what IS THE VARIANCE AT COMPLETION (vac)? SEE ATTACHEMENT POSSIBLE ANSWERS: 2046.9 -1216.0
REVIEW THE INTEGRATED PROGRAM MANAGEMENT REPORT (ipmr) EXCERPT FOR THE prime VEHICLE. what IS THE VARIANCE AT COMPLETION (vac)?
SEE ATTACHEMENT
POSSIBLE ANSWERS:
2046.9
-1216.0
-1438.5
543.3

Given sample Earned Value Management (EVM) data, calculate SV, SV %, CV, CV %, VAC, and VAC % Question 10 of 10. Integrated Program Management Report, Format 1 8. Performance Data Cumulative to Date At Completion Item Budgeted Cost BCWS | BCWP ACWP Variance |Schedule Cost Budgeted Estimated Variance 1.1 - Prime Vehicle 24626.1 23187.6 25234.5 -1438.5 -2046.9 36301.4 37517.4 Review the Integrated Program Management Report (IPMR) excerpt for the Prime Vehicle. What is the Variance at Completion (VAC)? (IMAGE DESCRIPTION: Performance data for item 1.1 Prime Vehicle is as follows: cumulative BCWS is 24626.1; cumulative BCWP is 23187.6; cumulative ACWP is 25234.5; cumulative schedule variance is 1438.5; and cumulative cost variance is 2046.9. Budget at completion is 36301.4 and estimate at completion is 37517.4.) O 2046.9 -1,216.0 O -1,438.5 543.3
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts