Question: Review the solution of the Johnsons 2 machine algorithm posted in Moodle as solution of the problem #4(Which is mentioned below as previous problem #4).
Review the solution of the Johnsons 2 machine algorithm posted in Moodle as solution of the problem #4(Which is mentioned below as previous problem #4).
Select a schedule of your choice and check if you can get a solution better than make span of 32 time units. Provide rationale for the schedule selected.
Previous Problem #4
Use Johnsons algorithm to find the optimal sequence of the following two machine problem. Estimate the L1 and L2 limits of the optimal sequence and the make span. Make span is associated with a static schedule and is defined as the time required to complete the schedule. The data show processing time on machine1 and machine2 respectively. Follow the example worked out in the note. The key issue is to understand the heuristic rules used.
Job M1 M2
1 4 6
2 5 3
3 2 7
4 3 4
5 8 4
6 6 5
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts