Question: Rey Custom Electronics (RCE) sells and installs complete security, computer, audio, and video systems for homes. On newly constructed homes it provides bids using time-and-material
Rey Custom Electronics (RCE) sells and installs complete security, computer, audio, and video systems for homes. On newly constructed homes it provides bids using time-and-material pricing. The following budgeted cost data are available.
| Time Charges | Material Loading Charges | ||||||
| Technicians' wages and benefits | $150,000 | - | |||||
| Parts manager's salary and benefits | - | $34,000 | |||||
| Office employee's salary and benefits | 30,000 | 15,000 | |||||
| Other overhead | 15,000 | 42,000 | |||||
| Total budgeted costs | $195,000 | $91,000 | |||||
The company has budgeted for 6,250 hours of technician time during the coming year. It desires a $38 profit margin per hour of labor and an 80% profit on parts. It estimates the total invoice cost of parts and materials in 2017 will be $700,000.
Compute the rate charged per hour of labor. (Round answer to 2 decimal places, e.g. 10.50.)
Compute the material loading percentage. (Round answer to 2 decimal places, e.g. 10.50.)
RCE has just received a request for a bid from Buil Builders on a $1,200,000 new home. The company estimates that it would require 80 hours of labor and $40,000 of parts. Compute the total estimated bill. (Round answer to 2 decimal places, e.g. 10.50.)