Question: Risk management planning: Select one: a. Is not static b. Is not a one-time process c. Cannot be assumed to be implemented on its own
Risk management planning:
Select one:
a.
Is not static
b.
Is not a one-time process
c.
Cannot be assumed to be implemented on its own
d.
All of these are correct.