Question: Risks should be managed Select one: a. As a routine part of recurring project team meetings b. Primarily at the end of each phase of
Risks should be managed
Select one:
a. As a routine part of recurring project team meetings
b. Primarily at the end of each phase of the project
c. By a person with a risk management certification from PMI
d. With the active daily involvement of the sponsor