Question: Rob is the project manager for a performance improvement initiative for a large hospital corporation. As part of his duties, he is consistently reviewing the

Rob is the project manager for a performance improvement initiative for a large hospital corporation. As part of his duties, he is consistently reviewing the current-status of the project and ensuring that activities are meeting their timeline. If Rob finds that activities are not meeting their timeline, he initiates changes to help the project get back on track. What phase of project management is Rob performing? a. Closure b. Monitoring and controlling c. Execution d. Initiation