Question: Roberto is using the 3 point estimate technique to estimate the duration of a particular activity. If the optimistic time is 20 hours , the
Roberto is using the 3 point estimate technique to estimate the duration of a particular activity. If the optimistic time is 20 hours , the most likely time is 24 hours and the pessimistic time is 31 hours, how long will the task take