Question: Ben's client asks him to fast-track a software development project. How can Ben comply with this request? 1. sequencing the highest-risk activities 2. overlapping the
Ben's client asks him to fast-track a software development project. How can Ben comply with this request?
1. sequencing the highest-risk activities
2. overlapping the longest-duration activities not on the critical path
3. overlapping some activities on the critical path
4. reducing lag times by 10 percent