Question: roblem 3 . 2 ( 1 0 pts ) Calculate the network below and answer the questions that follow. What is the project duration? What

roblem 3.2(10 pts)
Calculate the network below and answer the questions that follow.
What is the project duration?
What is the critical path?
What is the total float of activity E?
What is the free float of activity G?
What are the early start and finish dates of activity C?
What are the late start and finish dates of activity D?
Which activity(ies) has the largest total float?
Which activity has the largest free float?
What are the late start and finish dates of activity B?
If A was 5 days, how many days will the project duration be affected?