Question: Rodriguez, Inc., is preparing its direct labor budget for 2017 from the following production budget based on a calendar year. Quarter Units Quarter Units 1
Rodriguez, Inc., is preparing its direct labor budget for 2017 from the following production budget based on a calendar year.
| Quarter | Units | Quarter | Units | |||
| 1 | 20,500 | 3 | 35,480 | |||
| 2 | 25,100 | 4 | 30,140 |
Each unit requires 1.60 hours of direct labor. Prepare a direct labor budget for 2017. Wage rates are expected to be $15 for the first 2 quarters and $17 for quarters 3 and 4. (Round Direct labor time per unit answers to 2 decimal places, e.g. 52.50.)